Allergan Factory Upgrade, Westport, Co. Mayo
Overall Groundwork’s Sub – Contract
- Date: December 2012 – January 2012
- Client: John Sisk
- Project Type: Pharmaceutical
- Our Role: Sub – Contractor
About this Project
Some of the work we were required to complete as part of this factory upgrade project included:
- Site Clearance
- Internal Demolition of Mezzanine Floors and Internal Partitions
- Foundation Excavation
- Foul Water Drainage System incl Treatment System
- Storm Water Drainage System incl Rain Water Harvesting
- Watermain Installation
- Site Services
Roadways, Footpaths and Kerbing



Related Projects
Service Title
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Phasell sed nibh dignissim, cursus tellus sit amet, ultrices mauris. Aliquam
Service Title
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Phasell sed nibh dignissim, cursus tellus sit amet, ultrices mauris. Aliquam
Service Title
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Phasell sed nibh dignissim, cursus tellus sit amet, ultrices mauris. Aliquam